Staff photo by Bruce Preston |
MERRIMACK – Rock blasting has come to a
stop at the Merrimack Premium Outlet mall once again – this time, one
week before crews expected to complete the blasting work.
Town officials ordered the work suspended
last week after tests showed elevated nitrate levels in surface water
on the construction site, off Exit 10 of the F.E. Everett Turnpike.
The initial tests, conducted in late
September and early October, showed nitrate levels that reached 10 parts
per million – twice the amount permitted under the project’s
development agreement.
The project developer, Premium Outlets of
New Jersey, has since taken steps to correct the issue, and more recent
tests have shown lower rates, said Tim Thompson, Merrimack’s community
development director, who decided Friday to allow blasting to resume on
part of the construction site.
But town officials and consultants alike are awaiting further test results before they restore blasting fully, Thompson said.
“The monitoring is in place, and the
blasting has ceased,” he said. “As of now, there’s no imminent risk to
the wells. The drinking water is still safe.”
Project managers had expected to complete the blasting Tuesday, the same day of the next round of tests.
“This will obviously affect their schedule,” Thompson said Friday.
Blasting crews were forced to stop three
times over the winter after they exceeded permitted noise and vibration
levels. Prior to this instance, however, no issues had been reported
since February, when developers implemented a revised blasting plan.
Project officials believe this latest violation may be related to the heavy rains that fell over the last month.
“Our blasting plan worked as it was
designed,” said Michele Rothstein Sr. vice president of marketing for
the Simon Property Group. “As can happen with any construction project
that includes this type of work, recent heavy rains, including Hurricane
Irene, contributed to the runoff of some materials from our site’s
surface.
“Our water-testing wells detected this
situation, and we suspended blasting, as called for in our plan. We have
nearly completed our blasting program and expect to resume the few
remaining blasts early next week.”
Following a major rain storm on Oct. 4,
representatives from Emery and Garrett Groundwater, the town’s water
consultant, noticed a breach in a trench that allowed rainwater to reach
a nearby wellhead protection area.
This water, which likely picked up
nitrates as it flowed downhill, likely contributed to the raised levels
within the protection area, according to Premium Outlets officials and
representatives from the Merrimack Village District, the town’s water
provider.
“There is (nitrate) in the blasting
compound they use,” Village District Superintendent Ron Minor said
Friday. “At this time, the nitrate levels do not threaten the quality of
the groundwater.”
Responding to the initial test results,
work crews immediately replaced pumps and repaired the site de-watering
system, Premium Outlet officials wrote in a company release Friday.
They increased the frequency of water sampling and testing, and they’ve issued a revised blasting sequence, Thompson said.
“They’ve been very cooperative,” he said.
But town officials are still waiting for
further test results before they allow blasting to resume within the
groundwater protection area.
“We’re paying more attention,” Minor said.
Meanwhile, other construction work has
continued on the site, according to the project developers. Frames and
walls are in place for three buildings on the northernmost side of the
construction site, with three other buildings quickly following suit.
About half of the parking areas have been paved, and landscaping work has started, developers wrote in the company release.
Despite the blasting delays, the project is still expected to be complete and open by summer, they said.
When it’s complete, the $100 million
project is expected to include 100 high-end retail stores. It’s
projected to generate more than $140 million in retail sales each year
and to create as many as 800 full- and part-time retail jobs.
Last year, project opponent Michael Mills
filed a lawsuit against Premium Outlets as construction began, accusing
the developer of failing to adhere to the water-testing conditions
required under the development agreement.
A Hillsborough County Superior Court judge
dismissed the suit in December, saying that, as an individual, Mills
can’t enforce the town’s contract.
Mills couldn’t be reached Friday for comment.
“The petitioner does not have any legal
rights under the agreement between the Town of Merrimack and (Merrimack
Premium Outlets),” Judge Jacalyn Colburn, of Hillsborough County
Superior Court, wrote in her initial decision.
Mills “does not have any cognizable claim against (the developer) to enforce the conditions contained in the … plan.”
No comments:
Post a Comment